On Tuesday April 25, 2023 the City of The Dalles Public Works will be begin work on several pavement resurfacing projects. Phase 1 of the project will be grinding out the old pavement. Phase 2 will be paving back new asphalt. All projects are expected to be completed by mid-May, weather permitting.
Work hours are from 7:00 a.m. to 5:00 p.m. on each scheduled work day. Full street closures will be in effect most of each work day. Motor vehicles and bicyclists will be detoured to adjacent side streets.
Where sidewalks exist, pedestrian and sidewalk access will remain open through the duration of this work.
No parking will be allowed within the project areas due to curb-to-curb asphalt removal and replacement. No parking signs will be place on the curb 48 hours before the project moves into each work area.
If you have questions, please contact the Public Works Department at (541) 296-5401 or call the after hours number at (541) 980-7703.
Resurfacing Project Schedule | |
Grind-Out All Sites 4/25-27/2023 | Pave-Back |
Brentwood Dr. | 5/1-4/2023 |
Crest Ct. | 5/1-4/2023 |
E. 11th St. | 5/8-11/2023 |
E. 13th Pl. | 5/8-11/2023 |
E. 18th St. | 5/15-16/2023 |
Bridge St. | 5/17-18/2023 |
–end–