Pavement Resurfacing Projects in The Dalles

On Tuesday April 25, 2023 the City of The Dalles Public Works will be begin work on several pavement resurfacing projects. Phase 1 of the project will be grinding out the old pavement. Phase 2 will be paving back new asphalt. All projects are expected to be completed by mid-May, weather permitting.

Work hours are from 7:00 a.m. to 5:00 p.m. on each scheduled work day. Full street closures will be in effect most of each work day. Motor vehicles and bicyclists will be detoured to adjacent side streets.

Where sidewalks exist, pedestrian and sidewalk access will remain open through the duration of this work.

Resurfacing Project Schedule
Grind-Out All Sites 4/25-27/2023Pave-Back
Brentwood Dr.5/1-4/2023
Crest Ct.5/1-4/2023
E. 11th St.5/8-11/2023
E. 13th Pl.5/8-11/2023
E. 18th St.5/15-16/2023
Bridge St. 5/17-18/2023

No parking will be allowed within the project areas due to curb-to-curb asphalt removal and replacement. No parking signs will be place on the curb 48 hours before the project moves into each work area.

If you have questions, please contact the Public Works Department at (541) 296-5401 or call the after hours number at (541) 980-7703.