Public Notice for Hostetler & W 10th St for School

With the start of school right around the corner we are racing to allow traffic to pass thru W 10th St for access.

Paving is scheduled for the main reconstructed area between Hostetler and Floral September 2nd; on this day the street will remain closed allowing for paving following the attached traffic control plan. The new sidewalk will be open for pedestrians, allowing kids to walk to school. Given that the project spans longer than these two streets the new ADAs elsewhere will remain graveled with final paving happening during the weekend. The last part of the project will be a slurry seal from Chenowith Loop to Snipes which will require the full length of the project to be closed while the tar dries, which happens on a weekend as well.

Attached are the traffic control plans for reference.